Subject: | Re: MUX A power increase implemented ?
| Date: | Tue, 22 Jul 2003 20:22:57 +0100
| From: | "aa" <me@privacy.net>
| Newsgroups: | uk.tech.digital-tv
|
"Roger" <noone@aol.com> wrote in message
news:bfjh0p$g1a$1@newsg3.svr.pol.co.uk
> The MUX A power increase at Winter Hill is supposed to be implemented
> in July. AFAIK it hasn't been done yet. Does anybody know whether the
> MUX A increases at Rowridge and Mendip which were also scheduled for
> July have been implemented.
Ok here's the latest update from those in the know..
Rowridge / Emley Moor / Huntshaw Cross / Sandy Heath - all completed last
week.
Winter Hill / Caradon Hill - completed today.
Mendip - to be completed btwn. 5 - 6 am on 24 July.
Hope that helps.
--
aa
'Reply-To' is valid
|